Here's a challenge MODLOGIQ delivered on beautifully—full turnkey execution of a bank branch project…from design assist to Certificate of Occupancy. Thanks to close collaboration between MODLOGIQ, the owner and the architect/design and construction management partners, this national bank branch opened less than 100 days after award of building permit.
For this turnkey project, MODLOGIQ’s Design Assist team worked with the Owner’s Architect of Record to convert the original design intended for conventional, stick-built construction into a modular project that could be built off-site in our New Holland plant to a 90% completion level, and then transported, installed and completed at the site.
We challenge you to find an off-site modular construction company that achieves 85% to 95% completion levels at the plant. AND delivers a 100% turnkey solution—from demo of the existing building on the property all the way through Certificate of Occupancy.
The challenge—transport across 1,400 miles all the modules, high hats, and parapets needed to erect a ~3,500 SF retail bank branch in Blue Springs, MO. It took efficient engineering. Careful route planning. Rugged protective wraps. Specialized lowboy trailers. Meticulous staging. And pinpoint coordination. At MODLOGIQ, smooth, seamless transport is just one more aspect of our turnkey solutions—making it possible to open a retail bank branch less than 100 days after permitting.
Finishing strong was a challenge that MODLOGIQ successfully met for this turnkey retail bank project. It’s how we helped our client open their retail bank branch less than 100 days after permitting.
That's the 100-day CHALLENGE! It's executing a fully-turnkey retail bank branch project -- from demolition of an existing building at the site to Certificate of Occupancy and doors open for business–less than 100 days after permitting.
That includes working with the Owner’s Architect of Record to convert the original design into a modular project that could be built off-site in our New Holland plant.
That includes all the site work from parking lots to ATMs to landscaping.
That includes finishing off-site construction in our plant to an 85% completion level.
That includes transport more than 1,000 miles.
That includes installation in about 72 hours.
That includes completion of the installed building at the site.
Finally, this project was leveraged as the pilot for a longer-term prototype program that will accelerate the roll out of branches across multiple markets. The benefits? Schedule acceleration, budget certainty, superior quality, least site impact, and a greener way of building.
From demolition of an existing building at the site…to Certificate of Occupancy, our experienced team can provide this same kind of turnkey solution to national/regional brands, including: